Bharatpur. The power infrastructure in the Bharatpur region is set for a significant upgrade as authorities work to install a massive new transformer at the Amoli-Chhonkarwara Grid Substation. This project, aimed at bolstering electricity supply for Vair, Bhusawar, and Mahwa, involves the deployment of a 160 MVA capacity unit that will effectively double the substation's current operational capability.
Transporting the equipment has proven to be a complex logistical challenge for the department. The transformer, measuring 17 feet in width and 40 feet in length, remained stationed at the Amoli toll plaza for four days as officials navigated the difficulties of moving such a large load through local transit routes. The size of the unit made it impossible to pass through existing narrow lanes and residential areas without significant modifications to the path.
To ensure the safe arrival of the equipment, the electricity department initiated a clearance operation along the route from Amoli to Chhonkarwara. This process has required the temporary removal of structural protrusions from houses and the widening of specific street sections that were obstructing the transport vehicle. The department is working closely with local residents to manage these necessary adjustments to the infrastructure.
According to Assistant Engineer Vivek Kothari, the current 160 MVA capacity at the substation has been under immense pressure due to a rising number of consumers and the addition of new feeders. The existing infrastructure struggled to meet the growing demand, leading to the urgent need for this expansion. Once the new unit is fully integrated, the total capacity of the substation will reach 320 MVA, providing a more stable and reliable power supply to the surrounding regions.
The entire operation is being conducted under the direct supervision of Executive Engineer Sushil Kumar Chaudhary. A dedicated technical team, including engineers and field staff, remains stationed at the site to oversee the installation process and ensure that the transition to the higher capacity grid is completed efficiently. This upgrade marks a major step forward in addressing the long-standing power distribution challenges faced by the local communities.